Aubburn, Kandivali East
by S D Corporation Private Limited · Kandivali East, Mumbai 400101 · Map
- Launched
- Jul 2020First of 3 phases
- Possession (MahaRERA)
- Oct 2027Extended in all 3 phases
- Concrete structure
- 87%Weighted across 3 phases
- Booked
- 148 of 17386% · 144 in Jul 2026
- Buildings
- 33.7 acres
- MahaRERA complaints
- 19Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 21
- 2 BHK
- 77
- 3 BHK
- 66
- Other units
- 9
- Total units
- 173
- Buildings
- 3
- Land
- 3.7 acres
- Phases
- 3
- MahaRERA complaints
- 19
The 3 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Aubburn Wing B Mid-construction | P51800025637 | 1 | 57% | 100% | |
| Aubburn Wing A Mid-construction | P51800025641 | 66 | 87% | 72% | |
| Aubburn Wing C Mid-construction | P51800026064 | 97 | 87% | 95% |
Show updates by phase
Aubburn Wing B (P51800025637)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 57% | 0% | 1 | |
| 100% | 30% | 0% | 1 | |
| 100% | 30% | 0% | – | |
| 100% | 30% | 0% | 83 |
"–" means MahaRERA shows no figure for that update.
Aubburn Wing A (P51800025641)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 87% | 0% | 51 | |
| 100% | 87% | 0% | 48 | |
| 100% | 48% | 0% | 48 | |
| 100% | 48% | 0% | 35 |
"–" means MahaRERA shows no figure for that update.
Aubburn Wing C (P51800026064)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 87% | 0% | 96 | |
| 100% | 87% | 0% | 95 | |
| 100% | 32% | 0% | 95 | |
| 100% | 32% | 0% | 75 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Aubburn by S D Corporation Private Limited is a 173-unit MHADA-sanctioned project in Kandivali East, Mumbai 400101, registered with MahaRERA in 3 phases, with possession due in October 2027. 148 units booked out of total 173 units. The concrete structure (RCC) is 87% complete.
Read full summary
Aubburn is a MHADA-sanctioned project by S D Corporation Private Limited in Kandivali East, Mumbai 400101, registered with MahaRERA as 3 phases (P51800025637, P51800025641, P51800026064). The first phase was launched in July 2020. Together the phases have 173 units in 3 buildings: 164 homes (1, 2 and 3 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. All 3 phases are active on MahaRERA.
The registered possession date is October 2027; all 3 phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 87% complete and final finishes 0% complete. None of the 3 phases has its structure complete.
148 units booked out of total 173 units (86%). Since the July 2026 update, 4 more units have been booked.