Vihar Heights, Ghatkopar East
by Saptrishi Homes LLP · Ghatkopar East, Mumbai 400077 · Map
- Launched
- Aug 20205 yrs originally promised
- Possession (MahaRERA)
- Aug 2026Extended by 1 yr
- Concrete structure
- 60%Mid-construction
- Booked (free sale)
- 82 of 8992% · 24 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale82 booked out of 89 units
Rehab24 units for existing members
Total 113 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 94
- 2 BHK
- 19
- Total units
- 113
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 89
- Rehab units
- 24
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 60% | 20% | 82 | |
| 100% | 60% | 20% | – | |
| 100% | 60% | 20% | – | |
| 100% | 60% | 20% | 17 |
"–" means MahaRERA shows no figure for that update.
About this project
Vihar Heights by Saptrishi Homes LLP is a 113-unit MHADA-sanctioned project in Ghatkopar East, Mumbai 400077, launched in August 2020 with possession due in August 2026. 82 units booked out of 89 units for sale. The concrete structure (RCC) is 60% complete.
Read full summary
Vihar Heights is a MHADA-sanctioned project by Saptrishi Homes LLP in Ghatkopar East, Mumbai 400077, registered with MahaRERA as P51800026062. It was launched in August 2020. It has 113 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 113 units, 89 are for sale and 24 are rehab units for existing members.
Possession was due in August 2026, after an extension of 1 year from the original August 2025. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 60% complete, final finishes 20% complete.
82 units booked out of 89 units for sale (92%).