Marathon Neovalley Kaveri, Bhandup West

by M/S Nexzone Fiscal Services Pvt Ltd · Bhandup West, Mumbai 400078 · Map

Launched
Nov 2020First of 2 phases
Possession (MahaRERA)
Jun 2027Extended in both phases
Concrete structure
100%Weighted across 2 phases
Booked
528 of 56294% · 529 in Jul 2026
Buildings
20.1 acres
MahaRERA complaints
6Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
322
1 BHK
240
Total units
562
Buildings
2
Land
0.1 acres
Phases
2
MahaRERA complaints
6

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Marathon Neovalley Kaveri Wing A
Nearing possession
P51800026955269100%99%
Marathon Neovalley Kaveri Wing B
Nearing possession
P51800026970293100%89%
Show updates by phase

Marathon Neovalley Kaveri Wing A (P51800026955)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%266
100%95%0%268
100%34%0%258
100%0%0%259

"–" means MahaRERA shows no figure for that update.

Marathon Neovalley Kaveri Wing B (P51800026970)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%75%262
100%100%1%261
100%95%1%253
100%45%0%228

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services39%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 23%Dec 2025: Concrete structure (RCC) 66%Jul 2026: Concrete structure (RCC) 98%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 1%Jul 2026: Final finishes 1%Oct 2026: Final finishes 39%Excavation 100%Concrete structure (RCC) 100%Final finishes 39%

How to read construction stages

Compared with 3 similar projects in PIN 400078

Projects with 250–1,200 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400078
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 1 mth6 yrs 8 mths
Possession date extendedYes1 of 3
Possession date (MahaRERA)Jun 2027Dec 2027
Concrete structure (RCC)100%100%
Units booked94%94%
MahaRERA complaints (filed by or against the builder)60

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Marathon Neovalley Kaveri by M/S Nexzone Fiscal Services Pvt Ltd is a 562-unit BMC-sanctioned project in Bhandup West, Mumbai 400078, registered with MahaRERA in 2 phases, with possession due in June 2027. 528 units booked out of total 562 units. The concrete structure (RCC) is complete.

Read full summary

Marathon Neovalley Kaveri is a BMC-sanctioned project by M/S Nexzone Fiscal Services Pvt Ltd in Bhandup West, Mumbai 400078, registered with MahaRERA as 2 phases (P51800026955, P51800026970). The first phase was launched in November 2020. Together the phases have 562 units in 2 buildings, with 1 RK and 1 BHK homes as registered with MahaRERA. Both phases are active on MahaRERA.

The registered possession date is June 2027; both phases have an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 39% complete. Both phases have their structure complete.

528 units booked out of total 562 units (94%).