Sukoon Sra Chs Ltd-Wing-A. /Western Heights Cts 394-B&C-Wing, Malad East
by M V Q Developers · Malad East, Mumbai 400097 · Map
- Launched
- Nov 20204 yrs 7 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 1 yr 6 mths
- Concrete structure
- 100%Nearing possession
- Booked
- 138 of 17579% · 128 in Jul 2026
- Buildings
- 20.6 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 175
- Total units
- 175
- Buildings
- 2
- Land
- 0.6 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 50% | 138 | |
| 100% | 100% | 50% | 128 | |
| 100% | 100% | 50% | 114 | |
| 100% | 84% | 50% | 3 |
"–" means MahaRERA shows no figure for that update.
About this project
Sukoon Sra Chs Ltd-Wing-A. /Western Heights Cts 394-B&C-Wing by M V Q Developers is a 175-unit SRA-sanctioned project in Malad East, Mumbai 400097, launched in November 2020 with possession due in December 2026. 138 units booked out of total 175 units. The concrete structure (RCC) is complete.
Read full summary
Sukoon Sra Chs Ltd-Wing-A. /Western Heights Cts 394-B&C-Wing is an SRA-sanctioned project by M V Q Developers in Malad East, Mumbai 400097, registered with MahaRERA as P51800027118. It was launched in November 2020. It has 175 units in 2 buildings, with 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, extended by 1 year 6 months from the original June 2025. Construction: excavation complete, structure (RCC) complete, final finishes 50% complete.
138 units booked out of total 175 units (79%). Since the July 2026 update, 10 more units have been booked.