Himat Mansion Chs Ltd, Borivali West
Ready to move
by Bhatia Builders And Developers Pvt Ltdc · Borivali West, Mumbai 400092 · Map
- Launched
- Nov 20206 yrs 7 mths promised
- Possession (MahaRERA)
- Jun 2027Not extended
- Concrete structure
- 100%Ready to move
- Booked
- 75 of 7699%
- Buildings
- 11.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 76
- Total units
- 76
- Buildings
- 1
- Land
- 1.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 75 | |
| 100% | 100% | 100% | 75 | |
| 100% | 100% | 0% | 75 | |
| 100% | 100% | 0% | 54 |
"–" means MahaRERA shows no figure for that update.
About this project
Himat Mansion Chs Ltd by Bhatia Builders And Developers Pvt Ltdc is a 76-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in November 2020 with possession due in June 2027. 75 units booked out of total 76 units. The concrete structure (RCC) is complete.
Read full summary
Himat Mansion Chs Ltd is a BMC-sanctioned project by Bhatia Builders And Developers Pvt Ltdc in Borivali West, Mumbai 400092, registered with MahaRERA as P51800027152. It was launched in November 2020. It has 76 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is June 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.
75 units booked out of total 76 units (99%).