Shradha Residency, Andheri West
by Konark Shradha Realtors · Andheri West, Mumbai 400058 · Map
- Launched
- Nov 20202 yrs 7 mths originally promised
- Possession (MahaRERA)
- Jul 2027Extended by 4 yrs 1 mth
- Concrete structure
- 85%Mid-construction
- Booked (free sale)
- 13 of 2259% · 39 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale13 booked out of 22 units
Rehab39 units for existing members
Total 61 units. Rehab units are not for sale.
Project facts
- 1 RK
- 16
- 1 BHK
- 16
- 2 BHK
- 12
- 4 BHK
- 2
- Other units
- 15
- Total units
- 61
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 22
- Rehab units
- 39
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 85% | 0% | 13 | |
| 100% | 85% | 0% | 13 | |
| 100% | 85% | 0% | 13 | |
| 100% | 80% | 0% | 1 |
"–" means MahaRERA shows no figure for that update.
About this project
Shradha Residency by Konark Shradha Realtors is a 61-unit BMC-sanctioned project in Andheri West, Mumbai 400058, launched in November 2020 with possession due in July 2027. 13 units booked out of 22 units for sale. The concrete structure (RCC) is 85% complete.
Read full summary
Shradha Residency is a BMC-sanctioned project by Konark Shradha Realtors in Andheri West, Mumbai 400058, registered with MahaRERA as P51800027190. It was launched in November 2020. It has 61 units in 1 building: 46 homes (1 RK, 1 BHK, 2 BHK and 4 BHK) and 15 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 61 units, 22 are for sale and 39 are rehab units for existing members.
Its registered possession date is July 2027, extended by 4 years 1 month from the original June 2023. Construction: excavation complete, structure (RCC) 85% complete, final finishes not started.
13 units booked out of 22 units for sale (59%).