Sheth Cnergy Malad, Malad East
by Sheth Developers Private Limited · Malad East, Mumbai 400097 · Map
- Launched
- Nov 20202 yrs 7 mths originally promised
- Possession (MahaRERA)
- Mar 2028Extended by 4 yrs 9 mths
- Concrete structure
- 0%Early stage
- Booked
- 29 of 4564% · 41 in Jul 2026
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 45
- Total units
- 45
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 29 | |
| 100% | 0% | 0% | 41 | |
| 100% | 0% | 0% | 41 | |
| 100% | 0% | 0% | 41 |
"–" means MahaRERA shows no figure for that update.
About this project
Sheth Cnergy Malad by Sheth Developers Private Limited is a 45-unit BMC-sanctioned project in Malad East, Mumbai 400097, launched in November 2020 with possession due in March 2028. 29 units booked out of total 45 units. Work on the concrete structure (RCC) has not started.
Read full summary
Sheth Cnergy Malad is a BMC-sanctioned project by Sheth Developers Private Limited in Malad East, Mumbai 400097, registered with MahaRERA as P51800027269. It was launched in November 2020. It has 45 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is March 2028, extended by 4 years 9 months from the original June 2023. Construction: excavation complete, structure (RCC) not started, final finishes not started.
29 units booked out of total 45 units (64%). Since the July 2026 update, the possession date has moved from June 2024 to March 2028.