O And S Royale, Ghatkopar West
Ready to move
by Suchita Orange Project Royale · Ghatkopar West, Mumbai 400086 · Map
- Launched
- Dec 20206 yrs promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 47 of 6276% · 73 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale47 booked out of 62 units
Rehab73 units for existing members
Total 135 units. Rehab units are not for sale.
Project facts
- 1 RK
- 2
- 1 BHK
- 111
- 2 BHK
- 7
- Other units
- 15
- Total units
- 135
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 62
- Rehab units
- 73
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 92% | 47 | |
| 100% | 100% | 92% | 47 | |
| 100% | 100% | 50% | 45 | |
| 100% | 100% | 50% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
O And S Royale by Suchita Orange Project Royale is a 135-unit SRA-sanctioned project in Ghatkopar West, Mumbai 400086, launched in December 2020 with possession due in December 2026. 47 units booked out of 62 units for sale. The concrete structure (RCC) is complete.
Read full summary
O And S Royale is an SRA-sanctioned project by Suchita Orange Project Royale in Ghatkopar West, Mumbai 400086, registered with MahaRERA as P51800027371. It was launched in December 2020. It has 135 units in 1 building: 120 homes (1 RK, 1 BHK and 2 BHK) and 15 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 135 units, 62 are for sale and 73 are rehab units for existing members.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 92% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
47 units booked out of 62 units for sale (76%).