Shivkunj, Jogeshwari East

by Shraddha Lifestyle LLP · Jogeshwari East, Mumbai 400060 · Map

Launched
Dec 20205 yrs 6 mths originally promised
Possession (MahaRERA)
Jun 2027Extended by 1 yr
Concrete structure
92%Mid-construction
Booked (free sale)
48 of 6376% · 19 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale48 booked out of 63 units

Rehab19 units for existing members

Total 82 units. Rehab units are not for sale.

Project facts

1 RK
1
1 BHK
48
2 BHK
29
Other units
4
Total units
82
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
63
Rehab units
19
Reserved units
17

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)92%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 66%Dec 2025: Concrete structure (RCC) 65%Jul 2026: Concrete structure (RCC) 90%Oct 2026: Concrete structure (RCC) 92%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 92%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%92%0%48
100%90%0%47
100%65%0%–
100%66%0%17

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Shivkunj by Shraddha Lifestyle LLP is an 82-unit BMC-sanctioned project in Jogeshwari East, Mumbai 400060, launched in December 2020 with possession due in June 2027. 48 units booked out of 63 units for sale. The concrete structure (RCC) is 92% complete.

Read full summary

Shivkunj is a BMC-sanctioned project by Shraddha Lifestyle LLP in Jogeshwari East, Mumbai 400060, registered with MahaRERA as P51800027559. It was launched in December 2020. It has 82 units in 1 building: 78 homes (1 RK, 1 BHK and 2 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 82 units, 63 are for sale and 19 are rehab units for existing members.

Its registered possession date is June 2027, extended by 1 year from the original June 2026. Construction: excavation complete, structure (RCC) 92% complete, final finishes not started.

48 units booked out of 63 units for sale (76%). Since the July 2026 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 90% to 92%.