72 Parksyde, Ghatkopar East

by Adeshwar Associates Nx · Ghatkopar East, Mumbai 400075 · Map

Launched
Jan 20216 yrs 5 mths promised
Possession (MahaRERA)
Jun 2027Not extended
Concrete structure
80%Mid-construction
Booked
–
Buildings
50.6 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
35
2 BHK
104
3 BHK
33
4 BHK
4
Other units
8
Total units
184
Buildings
5
Land
0.6 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation80%
Concrete structure (slabs)80%
Finishes, lifts and services76%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 80%Dec 2025: Excavation 80%Jul 2026: Excavation 80%Dec 2024: Concrete structure (RCC) 80%Dec 2025: Concrete structure (RCC) 80%Jul 2026: Concrete structure (RCC) 80%Dec 2024: Final finishes 68%Dec 2025: Final finishes 76%Jul 2026: Final finishes 76%Excavation 80%Concrete structure (RCC) 80%Final finishes 76%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
80%80%76%–
80%80%76%–
80%80%68%96

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

72 Parksyde by Adeshwar Associates Nx is a 184-unit project in Ghatkopar East, Mumbai 400075, launched in January 2021 with possession due in June 2027. The concrete structure (RCC) is 80% complete.

Read full summary

72 Parksyde is a project by Adeshwar Associates Nx in Ghatkopar East, Mumbai 400075, registered with MahaRERA as P51800027845. It was launched in January 2021. It has 184 units in 5 buildings: 176 homes (1, 2, 3 and 4 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2027, unchanged since launch. Construction: excavation 80% complete, structure (RCC) 80% complete, final finishes 76% complete.