Transcon Triumph, Andheri West
by Transcon Triumph Phase 2 Private Limited · Andheri West, Mumbai 400053 · Map
- Launched
- Jan 2021First of 3 phases
- Possession (MahaRERA)
- Sep 2026 – Jun 2027Extended in 1 of 3 phases
- Concrete structure
- 98%Weighted across 3 phases
- Booked
- 780 of 83194% · 776 in Jul 2026
- Buildings
- 30.3 acres
- MahaRERA complaints
- 27Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 192
- 2 BHK
- 481
- 3 BHK
- 149
- Other units
- 9
- Total units
- 831
- Buildings
- 3
- Land
- 0.3 acres
- Phases
- 3
- MahaRERA complaints
- 27
The 3 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Transcon Triumph Tower 2 Ready to move | P51800027978 | 324 | 100% | 96% | |
| Transcon Triumph Tower 3 Nearing possession | P51800030321 | 316 | 100% | 95% | |
| Transcon Triumph Tower 4 Mid-construction | P51800034924 | 182 | 89% | 88% |
Show updates by phase
Transcon Triumph Tower 2 (P51800027978)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 320 | |
| 100% | 100% | 96% | 318 | |
| 100% | 100% | 29% | – | |
| 100% | 75% | 17% | 285 |
"–" means MahaRERA shows no figure for that update.
Transcon Triumph Tower 3 (P51800030321)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 65% | 299 | |
| 100% | 100% | 58% | 297 | |
| 100% | 53% | 0% | 296 | |
| 100% | 53% | 0% | 282 |
"–" means MahaRERA shows no figure for that update.
Transcon Triumph Tower 4 (P51800034924)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 89% | 10% | 161 | |
| 100% | 86% | 10% | 161 | |
| 100% | 0% | 0% | 150 | |
| 100% | 0% | 0% | 74 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Transcon Triumph by Transcon Triumph Phase 2 Private Limited is an 831-unit SRA-sanctioned project in Andheri West, Mumbai 400053, registered with MahaRERA in 3 phases, with possession dates from September 2026 to June 2027. 780 units booked out of total 831 units. The concrete structure (RCC) is 98% complete.
Read full summary
Transcon Triumph is an SRA-sanctioned project by Transcon Triumph Phase 2 Private Limited in Andheri West, Mumbai 400053, registered with MahaRERA as 3 phases (P51800027978, P51800030321, P51800034924). The first phase was launched in January 2021. Together the phases have 831 units in 3 buildings: 822 homes (1, 2 and 3 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. All 3 phases are active on MahaRERA.
The phases' registered possession dates run from September 2026 to June 2027; 1 of 3 phases has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 98% complete and final finishes 67% complete. 2 of the 3 phases have their structure complete.
780 units booked out of total 831 units (94%). Since the July 2026 update, 4 more units have been booked.
Transcon's track record in Mumbai
MahaRERA projects registered 2017–2024 in Mumbai
| Projects registered with MahaRERA | 14 |
|---|---|
| Total units across these projects | 4,175 |
| Completed without extending the possession date | 3 |
| Completed after an extension | 0 |
| Lapsed | 3 |
| Under construction | 8 |
| Possession date extended on the builder's application | 2 |
| Typical time from launch to 100% structure | 7 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Transcon projects | 156 (13 of 14 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.