Prabhu Plaza, Malad West

Ready to move

by M/S United Housing Corporation · Malad West, Mumbai 400064 · Map

Launched
Feb 20215 yrs 4 mths originally promised
Possession (MahaRERA)
Mar 2027Extended by 9 mths
Concrete structure
100%Ready to move
Booked (free sale)
102 of 14670% · 60 rehab units
Buildings
20.9 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale102 booked out of 146 units

Rehab60 units for existing members

Total 206 units. Rehab units are not for sale.

Project facts

1 BHK
22
2 BHK
27
3 BHK
18
Other units
139
Total units
206
Buildings
2
Land
0.9 acres
Phases
1
MahaRERA complaints
1
Free-sale units
146
Rehab units
60

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 53%Dec 2025: Concrete structure (RCC) 80%Jul 2026: Concrete structure (RCC) 90%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 55%Dec 2025: Final finishes 65%Jul 2026: Final finishes 75%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%102
100%90%75%97
100%80%65%91
100%53%55%12

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400064

Projects with 30–150 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400064
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 4 mths4 yrs 2 mths
Possession date extendedBy 9 mths2 of 3
Possession date (MahaRERA)Mar 2027Dec 2026
Concrete structure (RCC)100%100%
MahaRERA complaints (filed by or against the builder)10

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Prabhu Plaza by M/S United Housing Corporation is a 206-unit BMC-sanctioned project in Malad West, Mumbai 400064, launched in February 2021 with possession due in March 2027. 102 units booked out of 146 units for sale. The concrete structure (RCC) is complete.

Read full summary

Prabhu Plaza is a BMC-sanctioned project by M/S United Housing Corporation in Malad West, Mumbai 400064, registered with MahaRERA as P51800028151. It was launched in February 2021. It has 206 units in 2 buildings: 67 homes (1, 2 and 3 BHK) and 139 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 206 units, 146 are for sale and 60 are rehab units for existing members.

Its registered possession date is March 2027, extended by 9 months from the original June 2026. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

102 units booked out of 146 units for sale (70%). Since the July 2026 update, 5 more units have been booked, the reported concrete structure (RCC) has gone from 90% to 100% and the possession date has moved from June 2026 to March 2027.