Purva Clermont, Mankhurd

by Puravankara Limited · Mankhurd, Mumbai 400088 · Map

Launched
Mar 2021First of 5 phases
Possession (MahaRERA)
Jun 2027Not extended
Concrete structure
93%Weighted across 5 phases
Booked
269 of 31685% · 254 in Jul 2026
Buildings
50.3 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
99
3 BHK
134
4 BHK
4
Other units
79
Total units
316
Buildings
5
Land
0.3 acres
Phases
5
MahaRERA complaints
1

The 5 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Purva Clermont Wing B
Nearing possession
P5180002842734100%76%
Purva Clermont Wing C
Mid-construction
P518000284285259%69%
Purva Clermont Wing E
Nearing possession
P518000284920100%87%
Purva Clermont Wing D
Ready to move
P5180002849499100%92%
Purva Clermont Wing A
Ready to move
P5180002857152100%90%
Show updates by phase

Purva Clermont Wing B (P51800028427)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%4%26
100%78%0%25
100%50%0%25
100%0%0%15

"–" means MahaRERA shows no figure for that update.

Purva Clermont Wing C (P51800028428)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%59%4%36
100%41%0%32
100%15%0%32
100%0%0%0

"–" means MahaRERA shows no figure for that update.

Purva Clermont Wing E (P51800028492)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%8%69
100%100%8%61
100%100%8%61
100%0%0%23

"–" means MahaRERA shows no figure for that update.

Purva Clermont Wing D (P51800028494)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%92%91
100%100%67%91
100%100%60%91
100%79%0%51

"–" means MahaRERA shows no figure for that update.

Purva Clermont Wing A (P51800028571)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%98%47
100%100%98%45
100%100%78%44
100%87%0%28

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)93%
Finishes, lifts and services48%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 39%Dec 2025: Concrete structure (RCC) 81%Jul 2026: Concrete structure (RCC) 88%Oct 2026: Concrete structure (RCC) 93%Dec 2024: Final finishes 0%Dec 2025: Final finishes 34%Jul 2026: Final finishes 39%Oct 2026: Final finishes 48%Excavation 100%Concrete structure (RCC) 93%Final finishes 48%

How to read construction stages

About this project

Purva Clermont by Puravankara Limited is a 316-unit BMC-sanctioned project in Mankhurd, Mumbai 400088, registered with MahaRERA in 5 phases, with possession due in June 2027. 269 units booked out of total 316 units. The concrete structure (RCC) is 93% complete.

Read full summary

Purva Clermont is a BMC-sanctioned project by Puravankara Limited in Mankhurd, Mumbai 400088, registered with MahaRERA as 5 phases (P51800028427, P51800028428, P51800028492, P51800028494, P51800028571). The first phase was launched in March 2021. Together the phases have 316 units in 5 buildings: 237 homes (2, 3 and 4 BHK) and 79 other units (shops, offices or not given by type), as registered with MahaRERA. All 5 phases are active on MahaRERA.

The registered possession date is June 2027; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 93% complete and final finishes 48% complete. 4 of the 5 phases have their structure complete.

269 units booked out of total 316 units (85%). Since the July 2026 update, 15 more units have been booked.

Puravankara's track record in Mumbai

MahaRERA projects registered 2021–2026 in Mumbai

Projects registered with MahaRERA7
Total units across these projects903
Completed without extending the possession date0
Completed after an extension0
Lapsed0
Under construction7
Possession date extended on the builder's application0
Typical time from launch to 100% structure4 years 9 months
MahaRERA complaints (filed by or against the builder), all Puravankara projects3 (2 of 7 projects)

See all Puravankara projects →