Purva Clermont, Mankhurd
by Puravankara Limited · Mankhurd, Mumbai 400088 · Map
- Launched
- Mar 2021First of 5 phases
- Possession (MahaRERA)
- Jun 2027Not extended
- Concrete structure
- 93%Weighted across 5 phases
- Booked
- 269 of 31685% · 254 in Jul 2026
- Buildings
- 50.3 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 99
- 3 BHK
- 134
- 4 BHK
- 4
- Other units
- 79
- Total units
- 316
- Buildings
- 5
- Land
- 0.3 acres
- Phases
- 5
- MahaRERA complaints
- 1
The 5 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Purva Clermont Wing B Nearing possession | P51800028427 | 34 | 100% | 76% | |
| Purva Clermont Wing C Mid-construction | P51800028428 | 52 | 59% | 69% | |
| Purva Clermont Wing E Nearing possession | P51800028492 | 0 | 100% | 87% | |
| Purva Clermont Wing D Ready to move | P51800028494 | 99 | 100% | 92% | |
| Purva Clermont Wing A Ready to move | P51800028571 | 52 | 100% | 90% |
Show updates by phase
Purva Clermont Wing B (P51800028427)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 4% | 26 | |
| 100% | 78% | 0% | 25 | |
| 100% | 50% | 0% | 25 | |
| 100% | 0% | 0% | 15 |
"–" means MahaRERA shows no figure for that update.
Purva Clermont Wing C (P51800028428)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 59% | 4% | 36 | |
| 100% | 41% | 0% | 32 | |
| 100% | 15% | 0% | 32 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Purva Clermont Wing E (P51800028492)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 8% | 69 | |
| 100% | 100% | 8% | 61 | |
| 100% | 100% | 8% | 61 | |
| 100% | 0% | 0% | 23 |
"–" means MahaRERA shows no figure for that update.
Purva Clermont Wing D (P51800028494)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 92% | 91 | |
| 100% | 100% | 67% | 91 | |
| 100% | 100% | 60% | 91 | |
| 100% | 79% | 0% | 51 |
"–" means MahaRERA shows no figure for that update.
Purva Clermont Wing A (P51800028571)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 98% | 47 | |
| 100% | 100% | 98% | 45 | |
| 100% | 100% | 78% | 44 | |
| 100% | 87% | 0% | 28 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Purva Clermont by Puravankara Limited is a 316-unit BMC-sanctioned project in Mankhurd, Mumbai 400088, registered with MahaRERA in 5 phases, with possession due in June 2027. 269 units booked out of total 316 units. The concrete structure (RCC) is 93% complete.
Read full summary
Purva Clermont is a BMC-sanctioned project by Puravankara Limited in Mankhurd, Mumbai 400088, registered with MahaRERA as 5 phases (P51800028427, P51800028428, P51800028492, P51800028494, P51800028571). The first phase was launched in March 2021. Together the phases have 316 units in 5 buildings: 237 homes (2, 3 and 4 BHK) and 79 other units (shops, offices or not given by type), as registered with MahaRERA. All 5 phases are active on MahaRERA.
The registered possession date is June 2027; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 93% complete and final finishes 48% complete. 4 of the 5 phases have their structure complete.
269 units booked out of total 316 units (85%). Since the July 2026 update, 15 more units have been booked.
Puravankara's track record in Mumbai
MahaRERA projects registered 2021–2026 in Mumbai
| Projects registered with MahaRERA | 7 |
|---|---|
| Total units across these projects | 903 |
| Completed without extending the possession date | 0 |
| Completed after an extension | 0 |
| Lapsed | 0 |
| Under construction | 7 |
| Possession date extended on the builder's application | 0 |
| Typical time from launch to 100% structure | 4 years 9 months |
| MahaRERA complaints (filed by or against the builder), all Puravankara projects | 3 (2 of 7 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.