Auris Ilaria, Malad West
by Transcon-Sheth Creators Private Limited · Malad West, Mumbai 400064 · Map
- Launched
- Mar 2021First of 2 phases
- Possession (MahaRERA)
- Oct 2027 – Apr 2028Not extended
- Concrete structure
- 59%Weighted across 2 phases
- Booked
- 757 of 84190% · 751 in Jul 2026
- Buildings
- 20.3 acres
- MahaRERA complaints
- 14Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 479
- 2 BHK
- 249
- 3 BHK
- 102
- 4 BHK
- 1
- Other units
- 10
- Total units
- 841
- Buildings
- 2
- Land
- 0.3 acres
- Phases
- 2
- MahaRERA complaints
- 14
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Auris Ilaria Tower A Nearing possession | P51800028533 | 487 | 100% | 96% | |
| Auris Ilaria Tower B Mid-construction | P51800033238 | 344 | 2% | 81% |
Show updates by phase
Auris Ilaria Tower A (P51800028533)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 477 | |
| 100% | 16% | 0% | 477 | |
| 100% | 16% | 0% | – | |
| 100% | 16% | 0% | 402 |
"–" means MahaRERA shows no figure for that update.
Auris Ilaria Tower B (P51800033238)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 2% | 0% | 280 | |
| 100% | 0% | 0% | 274 | |
| 100% | 0% | 0% | – | |
| 100% | 0% | 0% | 201 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Auris Ilaria by Transcon-Sheth Creators Private Limited is an 841-unit project in Malad West, Mumbai 400064, registered with MahaRERA in 2 phases, with possession dates from October 2027 to April 2028. 757 units booked out of total 841 units. The concrete structure (RCC) is 59% complete.
Read full summary
Auris Ilaria is a project by Transcon-Sheth Creators Private Limited in Malad West, Mumbai 400064, registered with MahaRERA as 2 phases (P51800028533, P51800033238). The first phase was launched in March 2021. Together the phases have 841 units in 2 buildings: 831 homes (1, 2, 3 and 4 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. Both phases are active on MahaRERA.
The phases' registered possession dates run from October 2027 to April 2028; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 59% complete and final finishes 0% complete. Neither phase has its structure complete.
757 units booked out of total 841 units (90%). Since the July 2026 update, 6 more units have been booked.
Transcon's track record in Mumbai
MahaRERA projects registered 2017–2024 in Mumbai
| Projects registered with MahaRERA | 14 |
|---|---|
| Total units across these projects | 4,175 |
| Completed without extending the possession date | 3 |
| Completed after an extension | 0 |
| Lapsed | 3 |
| Under construction | 8 |
| Possession date extended on the builder's application | 2 |
| Typical time from launch to 100% structure | 7 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Transcon projects | 156 (13 of 14 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.