Skip to main content

Pratap Grandeur, Malad East

by M/S Jpv Realtors · Malad East, Mumbai 400097 · Map

Launched
Mar 20214 yrs 3 mths originally promised
Possession (MahaRERA)
Jun 2027Extended by 2 yrs
Concrete structure
15%Mid-construction
Booked
12 of 1675%
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
9
3 BHK
7
Total units
16
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)15%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 15%Dec 2025: Concrete structure (RCC) 15%Jul 2026: Concrete structure (RCC) 15%Oct 2026: Concrete structure (RCC) 15%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 15%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%15%0%12
100%15%0%12
100%15%0%12
100%15%0%12

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Pratap Grandeur by M/S Jpv Realtors is a 16-unit BMC-sanctioned project in Malad East, Mumbai 400097, launched in March 2021 with possession due in June 2027. 12 units booked out of total 16 units. The concrete structure (RCC) is 15% complete.

Read full summary

Pratap Grandeur is a BMC-sanctioned project by M/S Jpv Realtors in Malad East, Mumbai 400097, registered with MahaRERA as P51800028713. It was launched in March 2021. It has 16 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2027, extended by 2 years from the original June 2025. Construction: excavation complete, structure (RCC) 15% complete, final finishes not started.

12 units booked out of total 16 units (75%).