Pratap Grandeur, Malad East
by M/S Jpv Realtors · Malad East, Mumbai 400097 · Map
- Launched
- Mar 20214 yrs 3 mths originally promised
- Possession (MahaRERA)
- Jun 2027Extended by 2 yrs
- Concrete structure
- 15%Mid-construction
- Booked
- 12 of 1675%
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 9
- 3 BHK
- 7
- Total units
- 16
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 15% | 0% | 12 | |
| 100% | 15% | 0% | 12 | |
| 100% | 15% | 0% | 12 | |
| 100% | 15% | 0% | 12 |
"–" means MahaRERA shows no figure for that update.
About this project
Pratap Grandeur by M/S Jpv Realtors is a 16-unit BMC-sanctioned project in Malad East, Mumbai 400097, launched in March 2021 with possession due in June 2027. 12 units booked out of total 16 units. The concrete structure (RCC) is 15% complete.
Read full summary
Pratap Grandeur is a BMC-sanctioned project by M/S Jpv Realtors in Malad East, Mumbai 400097, registered with MahaRERA as P51800028713. It was launched in March 2021. It has 16 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is June 2027, extended by 2 years from the original June 2025. Construction: excavation complete, structure (RCC) 15% complete, final finishes not started.
12 units booked out of total 16 units (75%).