Tower 28 - C and F, Malad East
by Shiv Shakti Builders And Developers · Malad East, Mumbai 400097 · Map
- Launched
- Mar 20214 yrs 3 mths originally promised
- Possession (MahaRERA)
- Dec 2027Extended by 2 yrs 6 mths
- Concrete structure
- 48%Mid-construction
- Booked
- 151 of 38339% · 133 in Jul 2026
- Buildings
- 22.8 acres
- MahaRERA complaints
- 4Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 315
- 3 BHK
- 58
- Other units
- 10
- Total units
- 383
- Buildings
- 2
- Land
- 2.8 acres
- Phases
- 1
- MahaRERA complaints
- 4
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 48% | 13% | 151 | |
| 40% | 0% | 0% | 133 | |
| 40% | 0% | 0% | 108 | |
| 40% | 0% | 0% | 79 |
"–" means MahaRERA shows no figure for that update.
About this project
Tower 28 - C and F by Shiv Shakti Builders And Developers is a 383-unit SRA-sanctioned project in Malad East, Mumbai 400097, launched in March 2021 with possession due in December 2027. 151 units booked out of total 383 units. The concrete structure (RCC) is 48% complete.
Read full summary
Tower 28 - C and F is an SRA-sanctioned project by Shiv Shakti Builders And Developers in Malad East, Mumbai 400097, registered with MahaRERA as P51800028777. It was launched in March 2021. It has 383 units in 2 buildings: 373 homes (2 and 3 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2027, extended by 2 years 6 months from the original June 2025. Construction: excavation complete, structure (RCC) 48% complete, final finishes 13% complete.
151 units booked out of total 383 units (39%). Since the July 2026 update, 18 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 48%.