Tower 28 - C and F, Malad East

by Shiv Shakti Builders And Developers · Malad East, Mumbai 400097 · Map

Launched
Mar 20214 yrs 3 mths originally promised
Possession (MahaRERA)
Dec 2027Extended by 2 yrs 6 mths
Concrete structure
48%Mid-construction
Booked
151 of 38339% · 133 in Jul 2026
Buildings
22.8 acres
MahaRERA complaints
4Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
315
3 BHK
58
Other units
10
Total units
383
Buildings
2
Land
2.8 acres
Phases
1
MahaRERA complaints
4

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)48%
Finishes, lifts and services13%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 40%Dec 2025: Excavation 40%Jul 2026: Excavation 40%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 48%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 13%Excavation 100%Concrete structure (RCC) 48%Final finishes 13%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%48%13%151
40%0%0%133
40%0%0%108
40%0%0%79

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Tower 28 - C and F by Shiv Shakti Builders And Developers is a 383-unit SRA-sanctioned project in Malad East, Mumbai 400097, launched in March 2021 with possession due in December 2027. 151 units booked out of total 383 units. The concrete structure (RCC) is 48% complete.

Read full summary

Tower 28 - C and F is an SRA-sanctioned project by Shiv Shakti Builders And Developers in Malad East, Mumbai 400097, registered with MahaRERA as P51800028777. It was launched in March 2021. It has 383 units in 2 buildings: 373 homes (2 and 3 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, extended by 2 years 6 months from the original June 2025. Construction: excavation complete, structure (RCC) 48% complete, final finishes 13% complete.

151 units booked out of total 383 units (39%). Since the July 2026 update, 18 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 48%.