Safal Montbay, Mankhurd
by Jai Mata Di Home Construction Pvt Ltd · Mankhurd, Mumbai 400088 · Map
- Launched
- Mar 20214 yrs 1 mth originally promised
- Possession (MahaRERA)
- Sep 2028Extended by 3 yrs 5 mths
- Concrete structure
- 0%Early stage
- Booked
- 4 of 2516%
- Buildings
- 20.8 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 3
- 3 BHK
- 7
- 4 BHK
- 5
- 5+ BHK
- 10
- Total units
- 25
- Buildings
- 2
- Land
- 0.8 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Work not started as of Oct 2026
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | 4 | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | – | |
| 0% | 0% | 0% | 4 |
"–" means MahaRERA shows no figure for that update.
About this project
Safal Montbay by Jai Mata Di Home Construction Pvt Ltd is a 25-unit BMC-sanctioned project in Mankhurd, Mumbai 400088, launched in March 2021 with possession due in September 2028. 4 units booked out of total 25 units. Work on the concrete structure (RCC) has not started.
Read full summary
Safal Montbay is a BMC-sanctioned project by Jai Mata Di Home Construction Pvt Ltd in Mankhurd, Mumbai 400088, registered with MahaRERA as P51800028789. It was launched in March 2021. It has 25 units in 2 buildings, with 2, 3, 4 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is September 2028, extended by 3 years 5 months from the original April 2025. Construction: excavation not started, structure (RCC) not started, final finishes not started.
4 units booked out of total 25 units (16%).