Prathamesh Star, Borivali West

by Sailee Developers Pvt Ltd · Borivali West, Mumbai 400091 · Map

Launched
Apr 20215 yrs 2 mths originally promised
Possession (MahaRERA)
Jun 2027Extended by 1 yr
Concrete structure
55%Mid-construction
Booked
57 of 6785% · 56 in Jul 2026
Buildings
10.3 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
29
3 BHK
22
4 BHK
16
Total units
67
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)55%
Finishes, lifts and services15%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 50%Dec 2025: Concrete structure (RCC) 50%Jul 2026: Concrete structure (RCC) 55%Oct 2026: Concrete structure (RCC) 55%Dec 2024: Final finishes 10%Dec 2025: Final finishes 10%Jul 2026: Final finishes 15%Oct 2026: Final finishes 15%Excavation 100%Concrete structure (RCC) 55%Final finishes 15%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%55%15%57
100%55%15%56
100%50%10%56
100%50%10%32

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Prathamesh Star by Sailee Developers Pvt Ltd is a 67-unit MHADA-sanctioned project in Borivali West, Mumbai 400091, launched in April 2021 with possession due in June 2027. 57 units booked out of total 67 units. The concrete structure (RCC) is 55% complete.

Read full summary

Prathamesh Star is a MHADA-sanctioned project by Sailee Developers Pvt Ltd in Borivali West, Mumbai 400091, registered with MahaRERA as P51800028896. It was launched in April 2021. It has 67 units in 1 building, with 1, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is June 2027, extended by 1 year from the original June 2026. Construction: excavation complete, structure (RCC) 55% complete, final finishes 15% complete.

57 units booked out of total 67 units (85%). Since the July 2026 update, 1 more unit has been booked.