Skip to main content

Celestial Living, Dahisar

by Oyster Living LLP · Dahisar, Mumbai 400068 · Map

Launched
Apr 20219 yrs 8 mths promised
Possession (MahaRERA)
Dec 2030Not extended
Concrete structure
0%Early stage
Booked
170 of 2,0408%
Buildings
75.4 acres
MahaRERA complaints
46Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
937
2 BHK
503
Other units
600
Total units
2,040
Buildings
7
Land
5.4 acres
Phases
1
MahaRERA complaints
46

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Work not started as of Oct 2026

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%170
0%0%0%–
0%0%0%–
0%0%0%170

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Celestial Living by Oyster Living LLP is a 2,040-unit project in Dahisar, Mumbai 400068, launched in April 2021 with possession due in December 2030. 170 units booked out of total 2,040 units. Work on the concrete structure (RCC) has not started.

Read full summary

Celestial Living is a project by Oyster Living LLP in Dahisar, Mumbai 400068, registered with MahaRERA as P51800028969. It was launched in April 2021. It has 2,040 units in 7 buildings: 1,440 homes (1 and 2 BHK) and 600 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2030, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.

170 units booked out of total 2,040 units (8%).