Southfield Gravity, Bhandup East

by Southfield Buildcon LLP · Bhandup East, Mumbai 400042 · Map

Launched
Apr 20212 yrs 10 mths originally promised
Possession (MahaRERA)
Apr 2027Extended by 3 yrs 2 mths
Concrete structure
100%Nearing possession
Booked
145 of 15594%
Buildings
21.3 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
112
2 BHK
43
Total units
155
Buildings
2
Land
1.3 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services25%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 25%Jul 2026: Final finishes 25%Oct 2026: Final finishes 25%Excavation 100%Concrete structure (RCC) 100%Final finishes 25%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%25%145
100%100%25%145
100%100%25%145
100%100%0%144

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Southfield Gravity by Southfield Buildcon LLP is a 155-unit BMC-sanctioned project in Bhandup East, Mumbai 400042, launched in April 2021 with possession due in April 2027. 145 units booked out of total 155 units. The concrete structure (RCC) is complete.

Read full summary

Southfield Gravity is a BMC-sanctioned project by Southfield Buildcon LLP in Bhandup East, Mumbai 400042, registered with MahaRERA as P51800029080. It was launched in April 2021. It has 155 units in 2 buildings, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is April 2027, extended by 3 years 2 months from the original February 2024. Construction: excavation complete, structure (RCC) complete, final finishes 25% complete.

145 units booked out of total 155 units (94%).