Star Heights, Santacruz East
by Starwood Builder And Developer · Santacruz East, Mumbai 400098 · Map
- Launched
- May 20212 yrs 1 mth originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 3 yrs 6 mths
- Concrete structure
- 100%Nearing possession
- Booked
- –
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 13
- 2 BHK
- 20
- Other units
- 5
- Total units
- 38
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 30% | – | |
| 100% | 100% | 30% | – | |
| 100% | 100% | 30% | – | |
| 100% | 100% | 30% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Star Heights by Starwood Builder And Developer is a 38-unit project in Santacruz East, Mumbai 400098, launched in May 2021 with possession due in December 2026. The concrete structure (RCC) is complete.
Read full summary
Star Heights is a project by Starwood Builder And Developer in Santacruz East, Mumbai 400098, registered with MahaRERA as P51800029196. It was launched in May 2021. It has 38 units in 1 building: 33 homes (1 and 2 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, extended by 3 years 6 months from the original June 2023. Construction: excavation complete, structure (RCC) complete, final finishes 30% complete.