Astrum, Malad East
by Upvan Developers · Malad East, Mumbai 400097 · Map
- Launched
- May 20213 yrs 7 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 2 yrs
- Concrete structure
- 100%Nearing possession
- Booked
- 63 of 6893% · 59 in Jul 2026
- Buildings
- 10.4 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 40
- 3 BHK
- 27
- 4 BHK
- 1
- Total units
- 68
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Reserved units
- 8
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 78% | 63 | |
| 100% | 86% | 38% | 59 | |
| 100% | 86% | 38% | 61 | |
| 100% | 26% | 0% | 49 |
"–" means MahaRERA shows no figure for that update.
About this project
Astrum by Upvan Developers is a 68-unit BMC-sanctioned project in Malad East, Mumbai 400097, launched in May 2021 with possession due in December 2026. 63 units booked out of total 68 units. The concrete structure (RCC) is complete.
Read full summary
Astrum is a BMC-sanctioned project by Upvan Developers in Malad East, Mumbai 400097, registered with MahaRERA as P51800029353. It was launched in May 2021. It has 68 units in 1 building, with 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, extended by 2 years from the original December 2024. Construction: excavation complete, structure (RCC) complete, final finishes 78% complete.
63 units booked out of total 68 units (93%). Since the July 2026 update, 4 more units have been booked, the reported concrete structure (RCC) has gone from 86% to 100% and the possession date has moved from December 2025 to December 2026.