Astrum, Malad East

by Upvan Developers · Malad East, Mumbai 400097 · Map

Launched
May 20213 yrs 7 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 2 yrs
Concrete structure
100%Nearing possession
Booked
63 of 6893% · 59 in Jul 2026
Buildings
10.4 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
40
3 BHK
27
4 BHK
1
Total units
68
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
1
Reserved units
8

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services78%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 26%Dec 2025: Concrete structure (RCC) 86%Jul 2026: Concrete structure (RCC) 86%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 38%Jul 2026: Final finishes 38%Oct 2026: Final finishes 78%Excavation 100%Concrete structure (RCC) 100%Final finishes 78%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%78%63
100%86%38%59
100%86%38%61
100%26%0%49

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Astrum by Upvan Developers is a 68-unit BMC-sanctioned project in Malad East, Mumbai 400097, launched in May 2021 with possession due in December 2026. 63 units booked out of total 68 units. The concrete structure (RCC) is complete.

Read full summary

Astrum is a BMC-sanctioned project by Upvan Developers in Malad East, Mumbai 400097, registered with MahaRERA as P51800029353. It was launched in May 2021. It has 68 units in 1 building, with 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 2 years from the original December 2024. Construction: excavation complete, structure (RCC) complete, final finishes 78% complete.

63 units booked out of total 68 units (93%). Since the July 2026 update, 4 more units have been booked, the reported concrete structure (RCC) has gone from 86% to 100% and the possession date has moved from December 2025 to December 2026.