Pearl Heaven, Andheri East
Ready to move
by Chandiwala Enterprises · Andheri East, Mumbai 400069 · Map
- Launched
- Jul 2021First of 3 phases
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 100%Weighted across 3 phases
- Booked (free sale)
- 196 of 19899%
- Buildings
- 31.9 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale196 booked out of 198 units
Land-owner share62 units, not for sale
Total 260 units. Land-owner units are not for sale.
Project facts
- 1 BHK
- 149
- 2 BHK
- 109
- 3 BHK
- 2
- Total units
- 260
- Buildings
- 3
- Land
- 1.9 acres
- Phases
- 3
- MahaRERA complaints
- 0
- Free-sale units
- 198
- Land-owner share (not for sale)
- 62
The 3 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Pearl Heaven IV Completed | P51800029797 | 0 | 100% | – | |
| Pearl Heaven III Completed | P51800049464 | 198 | 100% | 68% | |
| Pearl Heaven I Nearing possession | PR1182022501055 | 62 | 100% | 98% |
Show updates by phase
Pearl Heaven IV (P51800029797)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | – | |
| 100% | 100% | 100% | – | |
| 100% | 100% | 100% | 198 |
"–" means MahaRERA shows no figure for that update.
Pearl Heaven III (P51800049464)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 100% | 135 | |
| 100% | 100% | 100% | 135 | |
| 100% | 100% | 30% | – | |
| 100% | 100% | 30% | 51 |
"–" means MahaRERA shows no figure for that update.
Pearl Heaven I (PR1182022501055)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 63% | 61 | |
| 100% | 100% | 27% | 60 | |
| 100% | 94% | 25% | 27 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Pearl Heaven by Chandiwala Enterprises is a 260-unit SRA-sanctioned project in Andheri East, Mumbai 400069, registered with MahaRERA in 3 phases, with possession due in December 2027. 196 units booked out of 198 units for sale. The concrete structure (RCC) is complete.
Read full summary
Pearl Heaven is an SRA-sanctioned project by Chandiwala Enterprises in Andheri East, Mumbai 400069, registered with MahaRERA as 3 phases (P51800029797, P51800049464, PR1182022501055). The first phase was launched in July 2021. Together the phases have 260 units in 3 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. On MahaRERA, 2 are completed and 1 is active. Of the 260 units, 198 are for sale and 62 are the land-owner's share, not for sale.
The registered possession date is December 2027; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 100% complete and final finishes 91% complete. All 3 phases have their structure complete.
196 units booked out of 198 units for sale (99%).
Chandiwala's track record in Mumbai
MahaRERA projects registered 2017–2025 in Mumbai
| Projects registered with MahaRERA | 16 |
|---|---|
| Total units across these projects | 3,068 |
| Completed without extending the possession date | 7 |
| Completed after an extension | 1 |
| Lapsed | 0 |
| Under construction | 8 |
| Possession date extended on the builder's application | 1 |
| Typical time from launch to 100% structure | 1 year 10 months |
| MahaRERA complaints (filed by or against the builder), all Chandiwala projects | 1 (1 of 16 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.