Avant Heritage - III, Jogeshwari East
by Avant Heritage III Realty LLP · Jogeshwari East, Mumbai 400060 · Map
- Launched
- Jul 20214 yrs 5 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 1 yr
- Concrete structure
- 100%Nearing possession
- Booked
- 213 of 24487%
- Buildings
- 10.7 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 132
- 2 BHK
- 112
- Total units
- 244
- Buildings
- 1
- Land
- 0.7 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 68% | 213 | |
| 100% | 0% | 0% | 213 | |
| 100% | 0% | 0% | 213 | |
| 100% | 0% | 0% | 142 |
"–" means MahaRERA shows no figure for that update.
About this project
Avant Heritage - III by Avant Heritage III Realty LLP is a 244-unit SRA-sanctioned project in Jogeshwari East, Mumbai 400060, launched in July 2021 with possession due in December 2026. 213 units booked out of total 244 units. The concrete structure (RCC) is complete.
Read full summary
Avant Heritage - III is an SRA-sanctioned project by Avant Heritage III Realty LLP in Jogeshwari East, Mumbai 400060, registered with MahaRERA as P51800029940. It was launched in July 2021. It has 244 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, extended by 1 year from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes 68% complete.
213 units booked out of total 244 units (87%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 100%.