Bandra Boon Chs Ltd, Bandra West
by Mass Jaks Associate Ventures · Bandra West, Mumbai 400050 · Map
- Launched
- Jul 20213 yrs 5 mths originally promised
- Possession (MahaRERA)
- Dec 2025Extended by 1 yr
- Concrete structure
- 96%Mid-construction
- Booked (free sale)
- 22 of 2976% · 14 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale22 booked out of 29 units
Rehab14 units for existing members
Total 43 units. Rehab units are not for sale.
Project facts
- 1 RK
- 5
- 1 BHK
- 18
- 2 BHK
- 11
- 3 BHK
- 3
- 4 BHK
- 2
- Other units
- 4
- Total units
- 43
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 29
- Rehab units
- 14
- Reserved units
- 15
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 96% | 85% | 22 | |
| 100% | 0% | 0% | – | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400050
Projects with 10–80 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 5 mths | 5 yrs |
| Possession date extended | By 1 yr | 2 of 5 |
| Possession date (MahaRERA) | Dec 2025 | Dec 2027 |
| Concrete structure (RCC) | 96% | 0% |
| Units booked (free sale) | 76% | 52% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Godavari, Bandra West
- Magic Tower, Bandra West
- 25 West -A (East)Wing, Bandra West
- Prestige Daffodils Chsl, Bandra West
- Urban Waterfront, Bandra West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Godavari | April 2021 | December 2023 | 0% | 6 units booked out of total 21 units |
| Magic Tower | October 2021 | December 2027 | 9% | – |
| 25 West -A (East)Wing | March 2021 | June 2032 | 52% | 40 units booked out of total 65 units |
| Prestige Daffodils Chsl | December 2021 | December 2026 | 0% | 17 units booked out of 27 units for sale |
| Urban Waterfront | September 2020 | December 2031 | 0% | 11 units booked out of total 26 units |
About this project
Bandra Boon Chs Ltd by Mass Jaks Associate Ventures is a 43-unit SRA-sanctioned project in Bandra West, Mumbai 400050, launched in July 2021 with possession due in December 2025. 22 units booked out of 29 units for sale. The concrete structure (RCC) is 96% complete.
Read full summary
Bandra Boon Chs Ltd is an SRA-sanctioned project by Mass Jaks Associate Ventures in Bandra West, Mumbai 400050, registered with MahaRERA as P51800030090. It was launched in July 2021. It has 43 units in 1 building: 39 homes (1 RK, 1 BHK, 2 BHK, 3 BHK and 4 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 43 units, 29 are for sale and 14 are rehab units for existing members.
Possession was due in December 2025, after an extension of 1 year from the original December 2024. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 96% complete, final finishes 85% complete.
22 units booked out of 29 units for sale (76%).