Agarwal Floresta - Maple, Goregaon East
Ready to move
by Homewell Realty LLP · Goregaon East, Mumbai 400063 · Map
- Launched
- Jul 20215 yrs 5 mths promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 100%Ready to move
- Booked
- 207 of 207100% · 205 in Jul 2026
- Buildings
- 10.1 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 68
- 1 BHK
- 139
- Total units
- 207
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 2
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | 207 | |
| 100% | 100% | 33% | 205 | |
| 100% | 100% | 10% | 197 | |
| 100% | 97% | 0% | 168 |
"–" means MahaRERA shows no figure for that update.
About this project
Agarwal Floresta - Maple by Homewell Realty LLP is a 207-unit SRA-sanctioned project in Goregaon East, Mumbai 400063, launched in July 2021 with possession due in December 2026. 207 units booked out of total 207 units. The concrete structure (RCC) is complete.
Read full summary
Agarwal Floresta - Maple is an SRA-sanctioned project by Homewell Realty LLP in Goregaon East, Mumbai 400063, registered with MahaRERA as P51800030147. It was launched in July 2021. It has 207 units in 1 building, with 1 RK and 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
207 units booked out of total 207 units (100%). Since the July 2026 update, 2 more units have been booked.