Platinum Residency, Jogeshwari West

by Platinum Residency Co-Operative Housing Society Limited · Jogeshwari West, Mumbai 400102 · Map

Launched
Jul 20212 yrs 10 mths originally promised
Possession (MahaRERA)
Jul 2027Extended by 3 yrs 2 mths
Concrete structure
75%Mid-construction
Booked
34 of 13026% · 27 in Jul 2026
Buildings
41.7 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
1
2 BHK
87
3 BHK
5
Other units
37
Total units
130
Buildings
4
Land
1.7 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)75%
Finishes, lifts and services56%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 75%Dec 2025: Excavation 75%Jul 2026: Excavation 75%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 75%Dec 2025: Concrete structure (RCC) 75%Jul 2026: Concrete structure (RCC) 75%Oct 2026: Concrete structure (RCC) 75%Dec 2024: Final finishes 35%Dec 2025: Final finishes 35%Jul 2026: Final finishes 35%Oct 2026: Final finishes 56%Excavation 100%Concrete structure (RCC) 75%Final finishes 56%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%75%56%34
75%75%35%27
75%75%35%27
75%75%35%23

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Platinum Residency by Platinum Residency Co-Operative Housing Society Limited is a 130-unit BMC-sanctioned project in Jogeshwari West, Mumbai 400102, launched in July 2021 with possession due in July 2027. 34 units booked out of total 130 units. The concrete structure (RCC) is 75% complete.

Read full summary

Platinum Residency is a BMC-sanctioned project by Platinum Residency Co-Operative Housing Society Limited in Jogeshwari West, Mumbai 400102, registered with MahaRERA as P51800030148. It was launched in July 2021. It has 130 units in 4 buildings: 93 homes (1, 2 and 3 BHK) and 37 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is July 2027, extended by 3 years 2 months from the original May 2024. Construction: excavation complete, structure (RCC) 75% complete, final finishes 56% complete.

34 units booked out of total 130 units (26%). Since the July 2026 update, 7 more units have been booked and the possession date has moved from May 2025 to July 2027.