Platinum Residency, Jogeshwari West
by Platinum Residency Co-Operative Housing Society Limited · Jogeshwari West, Mumbai 400102 · Map
- Launched
- Jul 20212 yrs 10 mths originally promised
- Possession (MahaRERA)
- Jul 2027Extended by 3 yrs 2 mths
- Concrete structure
- 75%Mid-construction
- Booked
- 34 of 13026% · 27 in Jul 2026
- Buildings
- 41.7 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 1
- 2 BHK
- 87
- 3 BHK
- 5
- Other units
- 37
- Total units
- 130
- Buildings
- 4
- Land
- 1.7 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 75% | 56% | 34 | |
| 75% | 75% | 35% | 27 | |
| 75% | 75% | 35% | 27 | |
| 75% | 75% | 35% | 23 |
"–" means MahaRERA shows no figure for that update.
About this project
Platinum Residency by Platinum Residency Co-Operative Housing Society Limited is a 130-unit BMC-sanctioned project in Jogeshwari West, Mumbai 400102, launched in July 2021 with possession due in July 2027. 34 units booked out of total 130 units. The concrete structure (RCC) is 75% complete.
Read full summary
Platinum Residency is a BMC-sanctioned project by Platinum Residency Co-Operative Housing Society Limited in Jogeshwari West, Mumbai 400102, registered with MahaRERA as P51800030148. It was launched in July 2021. It has 130 units in 4 buildings: 93 homes (1, 2 and 3 BHK) and 37 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is July 2027, extended by 3 years 2 months from the original May 2024. Construction: excavation complete, structure (RCC) 75% complete, final finishes 56% complete.
34 units booked out of total 130 units (26%). Since the July 2026 update, 7 more units have been booked and the possession date has moved from May 2025 to July 2027.