Almeida Avana, Santacruz East
Ready to move
by D' Almeida Developers · Santacruz East, Mumbai 400029 · Map
- Launched
- Aug 20212 yrs 4 mths originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 3 yrs
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 3 of 1520% · 16 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale3 booked out of 15 units
Rehab16 units for existing members
Total 31 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 13
- 2 BHK
- 7
- 3 BHK
- 1
- 4 BHK
- 1
- Other units
- 9
- Total units
- 31
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 15
- Rehab units
- 16
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | 3 | |
| 100% | 100% | 95% | 3 | |
| 100% | 100% | 95% | 3 | |
| 100% | 100% | 95% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Almeida Avana by D' Almeida Developers is a 31-unit BMC-sanctioned project in Santacruz East, Mumbai 400029, launched in August 2021 with possession due in December 2026. 3 units booked out of 15 units for sale. The concrete structure (RCC) is complete.
Read full summary
Almeida Avana is a BMC-sanctioned project by D' Almeida Developers in Santacruz East, Mumbai 400029, registered with MahaRERA as P51800030236. It was launched in August 2021. It has 31 units in 1 building: 22 homes (1, 2, 3 and 4 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 31 units, 15 are for sale and 16 are rehab units for existing members.
Its registered possession date is December 2026, extended by 3 years from the original December 2023. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
3 units booked out of 15 units for sale (20%).