The Ace, Goregaon East
by Tanvi Construction Pvt Ltd · Goregaon East, Mumbai 400063 · Map
- Launched
- Aug 20213 yrs 4 mths originally promised
- Possession (MahaRERA)
- Apr 2029Extended by 4 yrs 4 mths
- Concrete structure
- 90%Mid-construction
- Booked
- 78 of 22235% · 70 in Jul 2026
- Buildings
- 10.9 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 222
- Total units
- 222
- Buildings
- 1
- Land
- 0.9 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 90% | 25% | 78 | |
| 100% | 85% | 0% | 70 | |
| 100% | 80% | 0% | 64 | |
| 80% | 36% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
The Ace by Tanvi Construction Pvt Ltd is a 222-unit project in Goregaon East, Mumbai 400063, launched in August 2021 with possession due in April 2029. 78 units booked out of total 222 units. The concrete structure (RCC) is 90% complete.
Read full summary
The Ace is a project by Tanvi Construction Pvt Ltd in Goregaon East, Mumbai 400063, registered with MahaRERA as P51800030288. It was launched in August 2021. It has 222 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is April 2029, extended by 4 years 4 months from the original December 2024. Construction: excavation complete, structure (RCC) 90% complete, final finishes 25% complete.
78 units booked out of total 222 units (35%). Since the July 2026 update, 8 more units have been booked, the reported concrete structure (RCC) has gone from 85% to 90% and the possession date has moved from March 2026 to April 2029.