- Launched
- Aug 20212 yrs 4 mths originally promised
- Possession (MahaRERA)
- Apr 2027Extended by 3 yrs 4 mths
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 10 of 1953% · 21 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale10 booked out of 19 units
Rehab21 units for existing members
Land-owner share2 units, not for sale
Total 42 units. Rehab and land-owner units are not for sale.
Project facts
- 2 BHK
- 25
- 3 BHK
- 8
- Other units
- 9
- Total units
- 42
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 19
- Rehab units
- 21
- Land-owner share (not for sale)
- 2
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | 10 | |
| 100% | 85% | 80% | 10 | |
| 100% | 85% | 45% | 11 | |
| 100% | 80% | 20% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Bella Casa by Konark Bella Casa LLP is a 42-unit BMC-sanctioned project in Andheri West, Mumbai 400058, launched in August 2021 with possession due in April 2027. 10 units booked out of 19 units for sale. The concrete structure (RCC) is complete.
Read full summary
Bella Casa is a BMC-sanctioned project by Konark Bella Casa LLP in Andheri West, Mumbai 400058, registered with MahaRERA as P51800030388. It was launched in August 2021. It has 42 units in 1 building: 33 homes (2 and 3 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 42 units, 19 are for sale, 21 are rehab units for existing members and 2 are the land-owner's share, not for sale.
Its registered possession date is April 2027, extended by 3 years 4 months from the original December 2023. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
10 units booked out of 19 units for sale (53%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 85% to 100% and the possession date has moved from December 2024 to April 2027.