93 Palladian, Andheri East

Ready to move

by Vijayalaxmi Builders & Contractors · Andheri East, Mumbai 400093 · Map

Launched
Aug 20212 yrs 10 mths originally promised
Possession (MahaRERA)
Oct 2028Extended by 4 yrs 4 mths
Concrete structure
100%Ready to move
Booked
112 of 11994%
Buildings
10.9 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
119
Total units
119
Buildings
1
Land
0.9 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 87%Dec 2025: Concrete structure (RCC) 95%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 20%Dec 2025: Final finishes 26%Jul 2026: Final finishes 100%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%112
100%100%100%112
100%95%26%105
100%87%20%66

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

93 Palladian by Vijayalaxmi Builders & Contractors is a 119-unit SRA-sanctioned project in Andheri East, Mumbai 400093, launched in August 2021 with possession due in October 2028. 112 units booked out of total 119 units. The concrete structure (RCC) is complete.

Read full summary

93 Palladian is an SRA-sanctioned project by Vijayalaxmi Builders & Contractors in Andheri East, Mumbai 400093, registered with MahaRERA as P51800030498. It was launched in August 2021. It has 119 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is October 2028, extended by 4 years 4 months from the original June 2024. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

112 units booked out of total 119 units (94%).