Harmony, Kandivali West
by Shreenath Associates · Kandivali West, Mumbai 400067 · Map
- Launched
- Aug 20213 yrs 4 mths originally promised
- Possession (MahaRERA)
- Aug 2026Extended by 1 yr 8 mths
- Concrete structure
- 95%Mid-construction
- Booked
- 2 of 1811%
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 RK
- 1
- 1 BHK
- 11
- 2 BHK
- 5
- Other units
- 1
- Total units
- 18
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 95% | 0% | 2 | |
| 100% | 90% | 0% | 2 | |
| 0% | 0% | 0% | 2 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Harmony by Shreenath Associates is an 18-unit BMC-sanctioned project in Kandivali West, Mumbai 400067, launched in August 2021 with possession due in August 2026. 2 units booked out of total 18 units. The concrete structure (RCC) is 95% complete.
Read full summary
Harmony is a BMC-sanctioned project by Shreenath Associates in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800030510. It was launched in August 2021. It has 18 units in 1 building: 17 homes (1 RK, 1 BHK and 2 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Possession was due in August 2026, after an extension of 1 year 8 months from the original December 2024. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 95% complete, final finishes not started.
2 units booked out of total 18 units (11%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 90% to 95%.