Artteza, Santacruz West

by Sunvision Estates · Santacruz West, Mumbai 400054 · Map

Launched
Aug 20212 yrs 9 mths originally promised
Possession (MahaRERA)
May 2025Extended by 1 yr
Concrete structure
95%Mid-construction
Booked
66 of 8082%
Buildings
40.7 acres
MahaRERA complaints
4Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
80
Total units
80
Buildings
4
Land
0.7 acres
Phases
1
MahaRERA complaints
4

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)95%
Finishes, lifts and services50%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 50%Dec 2025: Concrete structure (RCC) 50%Jul 2026: Concrete structure (RCC) 95%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 50%Excavation 100%Concrete structure (RCC) 95%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%95%50%66
100%50%0%67
100%50%0%26

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Artteza by Sunvision Estates is an 80-unit BMC-sanctioned project in Santacruz West, Mumbai 400054, launched in August 2021 with possession due in May 2025. 66 units booked out of total 80 units. The concrete structure (RCC) is 95% complete.

Read full summary

Artteza is a BMC-sanctioned project by Sunvision Estates in Santacruz West, Mumbai 400054, registered with MahaRERA as P51800030554. It was launched in August 2021. It has 80 units in 4 buildings, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Possession was due in May 2025, after an extension of 1 year from the original May 2024. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 95% complete, final finishes 50% complete.

66 units booked out of total 80 units (82%).