Radiant 59, Andheri East

by Veer Jalaram Developers · Andheri East, Mumbai 400059 · Map

Launched
Sep 20215 yrs 3 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
80%Mid-construction
Booked
84 of 8797%
Buildings
31.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
43
2 BHK
44
Total units
87
Buildings
3
Land
1.4 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)80%
Finishes, lifts and services67%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 75%Dec 2025: Concrete structure (RCC) 75%Jul 2026: Concrete structure (RCC) 75%Oct 2026: Concrete structure (RCC) 80%Dec 2024: Final finishes 67%Dec 2025: Final finishes 67%Jul 2026: Final finishes 67%Oct 2026: Final finishes 67%Excavation 100%Concrete structure (RCC) 80%Final finishes 67%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%80%67%84
100%75%67%–
100%75%67%–
100%75%67%95

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Radiant 59 by Veer Jalaram Developers is an 87-unit BMC-sanctioned project in Andheri East, Mumbai 400059, launched in September 2021 with possession due in December 2026. 84 units booked out of total 87 units. The concrete structure (RCC) is 80% complete.

Read full summary

Radiant 59 is a BMC-sanctioned project by Veer Jalaram Developers in Andheri East, Mumbai 400059, registered with MahaRERA as P51800030749. It was launched in September 2021. It has 87 units in 3 buildings, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 80% complete, final finishes 67% complete.

84 units booked out of total 87 units (97%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 75% to 80%.