Solitaire Edge, Kandivali East

Ready to move

by Mahaveer Construction · Kandivali East, Mumbai 400101 · Map

Launched
Sep 20215 yrs 3 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
100%Ready to move
Booked
91 of 12772%
Buildings
11.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
76
2 BHK
22
3 BHK
28
Other units
1
Total units
127
Buildings
1
Land
1.4 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 10%Jul 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%91
100%100%10%91
100%100%0%65

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Solitaire Edge by Mahaveer Construction is a 127-unit SRA-sanctioned project in Kandivali East, Mumbai 400101, launched in September 2021 with possession due in December 2026. 91 units booked out of total 127 units. The concrete structure (RCC) is complete.

Read full summary

Solitaire Edge is an SRA-sanctioned project by Mahaveer Construction in Kandivali East, Mumbai 400101, registered with MahaRERA as P51800030831. It was launched in September 2021. It has 127 units in 1 building: 126 homes (1, 2 and 3 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

91 units booked out of total 127 units (72%).