Trienity 1 Phase II, Borivali West
by Trienity Prime Property Projects LLP · Borivali West, Mumbai 400092 · Map
- Launched
- Sep 20213 yrs 4 mths originally promised
- Possession (MahaRERA)
- Mar 2027Extended by 2 yrs 2 mths
- Concrete structure
- 90%Mid-construction
- Booked
- 0 of 400%
- Buildings
- 10.3 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 40
- Total units
- 40
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 90% | 35% | 0 | |
| 100% | 90% | 35% | 0 | |
| 100% | 90% | 35% | – | |
| 100% | 90% | 35% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Trienity 1 Phase II by Trienity Prime Property Projects LLP is a 40-unit BMC-sanctioned project in Borivali West, Mumbai 400092, launched in September 2021 with possession due in March 2027. 0 units booked out of total 40 units. The concrete structure (RCC) is 90% complete.
Read full summary
Trienity 1 Phase II is a BMC-sanctioned project by Trienity Prime Property Projects LLP in Borivali West, Mumbai 400092, registered with MahaRERA as P51800030871. It was launched in September 2021. It has 40 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is March 2027, extended by 2 years 2 months from the original January 2025. Construction: excavation complete, structure (RCC) 90% complete, final finishes 35% complete.
0 units booked out of total 40 units (0%).