Rushabh Apartment, Borivali East
by R R Builders · Borivali East, Mumbai 400066 · Map
- Launched
- Sep 20212 yrs 11 mths originally promised
- Possession (MahaRERA)
- Nov 2026Extended by 2 yrs 3 mths
- Concrete structure
- 63%Mid-construction
- Booked (free sale)
- 12 of 3238% · 47 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale12 booked out of 32 units
Rehab47 units for existing members
Total 79 units. Rehab units are not for sale.
Project facts
- 1 RK
- 49
- 2 BHK
- 27
- Other units
- 3
- Total units
- 79
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 32
- Rehab units
- 47
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 63% | 0% | 12 | |
| 100% | 63% | 0% | 12 | |
| 100% | 63% | 0% | 12 | |
| 100% | 63% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Rushabh Apartment by R R Builders is a 79-unit BMC-sanctioned project in Borivali East, Mumbai 400066, launched in September 2021 with possession due in November 2026. 12 units booked out of 32 units for sale. The concrete structure (RCC) is 63% complete.
Read full summary
Rushabh Apartment is a BMC-sanctioned project by R R Builders in Borivali East, Mumbai 400066, registered with MahaRERA as P51800030994. It was launched in September 2021. It has 79 units in 1 building: 76 homes (1 RK and 2 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 79 units, 32 are for sale and 47 are rehab units for existing members.
Its registered possession date is November 2026, extended by 2 years 3 months from the original August 2024. Construction: excavation complete, structure (RCC) 63% complete, final finishes not started.
12 units booked out of 32 units for sale (38%).