Mahakali Hills, Andheri East

by Mohid Construction Co · Andheri East, Mumbai 400093 · Map

Launched
Oct 20213 yrs 2 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 2 yrs
Concrete structure
67%Mid-construction
Booked
238 of 30578% · 215 in Jul 2026
Buildings
51 acre
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
203
Other units
102
Total units
305
Buildings
5
Land
1 acre
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)67%
Finishes, lifts and services13%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 73%Dec 2025: Excavation 44%Jul 2026: Excavation 60%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 20%Dec 2025: Concrete structure (RCC) 12%Jul 2026: Concrete structure (RCC) 40%Oct 2026: Concrete structure (RCC) 67%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 4%Oct 2026: Final finishes 13%Excavation 100%Concrete structure (RCC) 67%Final finishes 13%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%67%13%238
60%40%4%215
44%12%0%209
73%20%0%154

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Mahakali Hills by Mohid Construction Co is a 305-unit SRA-sanctioned project in Andheri East, Mumbai 400093, launched in October 2021 with possession due in December 2026. 238 units booked out of total 305 units. The concrete structure (RCC) is 67% complete.

Read full summary

Mahakali Hills is an SRA-sanctioned project by Mohid Construction Co in Andheri East, Mumbai 400093, registered with MahaRERA as P51800031191. It was launched in October 2021. It has 305 units in 5 buildings: 203 homes (1 BHK) and 102 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 2 years from the original December 2024. Construction: excavation complete, structure (RCC) 67% complete, final finishes 13% complete.

238 units booked out of total 305 units (78%). Since the July 2026 update, 23 more units have been booked and the reported concrete structure (RCC) has gone from 40% to 67%.