Sanghvi Edge, Santacruz East

by Sangvi Lifespace Private Limited · Santacruz East, Mumbai 400055 · Map

Launched
Oct 20215 yrs 2 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
55%Mid-construction
Booked
74 of 13754%
Buildings
20.5 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
105
2 BHK
19
3 BHK
12
Other units
1
Total units
137
Buildings
2
Land
0.5 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)55%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 55%Dec 2025: Concrete structure (RCC) 55%Jul 2026: Concrete structure (RCC) 55%Oct 2026: Concrete structure (RCC) 55%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 55%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%55%0%74
100%55%0%–
100%55%0%–
100%55%0%74

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Sanghvi Edge by Sangvi Lifespace Private Limited is a 137-unit BMC-sanctioned project in Santacruz East, Mumbai 400055, launched in October 2021 with possession due in December 2026. 74 units booked out of total 137 units. The concrete structure (RCC) is 55% complete.

Read full summary

Sanghvi Edge is a BMC-sanctioned project by Sangvi Lifespace Private Limited in Santacruz East, Mumbai 400055, registered with MahaRERA as P51800031420. It was launched in October 2021. It has 137 units in 2 buildings: 136 homes (1, 2 and 3 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 55% complete, final finishes not started.

74 units booked out of total 137 units (54%).