Arkan, Jogeshwari West
by Gajaanan Property Developers Private Limited · Jogeshwari West, Mumbai 400102 · Map
- Launched
- Oct 20214 yrs 2 mths originally promised
- Possession (MahaRERA)
- Apr 2028Extended by 2 yrs 4 mths
- Concrete structure
- 57%Mid-construction
- Booked
- 207 of 207100%
- Buildings
- 30.8 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 207
- Total units
- 207
- Buildings
- 3
- Land
- 0.8 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 33% | 57% | 0% | 207 | |
| 93% | 33% | 0% | 207 | |
| 70% | 0% | 0% | – | |
| 70% | 0% | 0% | 103 |
"–" means MahaRERA shows no figure for that update.
About this project
Arkan by Gajaanan Property Developers Private Limited is a 207-unit SRA-sanctioned project in Jogeshwari West, Mumbai 400102, launched in October 2021 with possession due in April 2028. 207 units booked out of total 207 units. The concrete structure (RCC) is 57% complete.
Read full summary
Arkan is an SRA-sanctioned project by Gajaanan Property Developers Private Limited in Jogeshwari West, Mumbai 400102, registered with MahaRERA as P51800031563. It was launched in October 2021. It has 207 units in 3 buildings, as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is April 2028, extended by 2 years 4 months from the original December 2025. Construction: excavation 33% complete, structure (RCC) 57% complete, final finishes not started.
207 units booked out of total 207 units (100%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 33% to 57% and the possession date has moved from December 2025 to April 2028.