Nahur Gaonthan Shiv Shakti Chs Ltd, Mulund West
Ready to move
by Om Builders And Developers · Mulund West, Mumbai 400080 · Map
- Launched
- Nov 20211 yr 1 mth originally promised
- Possession (MahaRERA)
- Jul 2027Extended by 4 yrs 7 mths
- Concrete structure
- 100%Ready to move
- Booked (free sale)
- 24 of 3275% · 238 rehab units
- Buildings
- 30.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale24 booked out of 32 units
Rehab238 units for existing members
Total 270 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 261
- 2 BHK
- 9
- Total units
- 270
- Buildings
- 3
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 32
- Rehab units
- 238
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 98% | 24 | |
| 100% | 100% | 98% | 24 | |
| 100% | 100% | 98% | 22 | |
| 100% | 100% | 98% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Nahur Gaonthan Shiv Shakti Chs Ltd by Om Builders And Developers is a 270-unit SRA-sanctioned project in Mulund West, Mumbai 400080, launched in November 2021 with possession due in July 2027. 24 units booked out of 32 units for sale. The concrete structure (RCC) is complete.
Read full summary
Nahur Gaonthan Shiv Shakti Chs Ltd is an SRA-sanctioned project by Om Builders And Developers in Mulund West, Mumbai 400080, registered with MahaRERA as P51800031723. It was launched in November 2021. It has 270 units in 3 buildings, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 270 units, 32 are for sale and 238 are rehab units for existing members.
Its registered possession date is July 2027, extended by 4 years 7 months from the original December 2022. Construction: excavation complete, structure (RCC) complete, final finishes 98% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
24 units booked out of 32 units for sale (75%).