Agarwal Floresta - Oak, Goregaon East
by Homewell Realty LLP · Goregaon East, Mumbai 400063 · Map
- Launched
- Nov 20215 yrs 7 mths promised
- Possession (MahaRERA)
- Jun 2027Not extended
- Concrete structure
- 72%Mid-construction
- Booked
- 160 of 17591% · 145 in Jul 2026
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 4
- 2 BHK
- 135
- 3 BHK
- 36
- Total units
- 175
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 72% | 20% | 160 | |
| 100% | 13% | 0% | 145 | |
| 100% | 15% | 0% | 117 | |
| 100% | 0% | 0% | 89 |
"–" means MahaRERA shows no figure for that update.
About this project
Agarwal Floresta - Oak by Homewell Realty LLP is a 175-unit SRA-sanctioned project in Goregaon East, Mumbai 400063, launched in November 2021 with possession due in June 2027. 160 units booked out of total 175 units. The concrete structure (RCC) is 72% complete.
Read full summary
Agarwal Floresta - Oak is an SRA-sanctioned project by Homewell Realty LLP in Goregaon East, Mumbai 400063, registered with MahaRERA as P51800031760. It was launched in November 2021. It has 175 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is June 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 72% complete, final finishes 20% complete.
160 units booked out of total 175 units (91%). Since the July 2026 update, 15 more units have been booked and the reported concrete structure (RCC) has gone from 13% to 72%.