The Palladium, Andheri East

by Fortune Reality · Andheri East, Mumbai 400059 · Map

Launched
Nov 20211 yr 1 mth originally promised
Possession (MahaRERA)
Apr 2028Extended by 5 yrs 4 mths
Concrete structure
85%Mid-construction
Booked
15 of 2075%
Buildings
18.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
20
Total units
20
Buildings
1
Land
8.3 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)85%
Finishes, lifts and services20%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 85%Dec 2025: Concrete structure (RCC) 85%Jul 2026: Concrete structure (RCC) 85%Oct 2026: Concrete structure (RCC) 85%Dec 2024: Final finishes 20%Dec 2025: Final finishes 20%Jul 2026: Final finishes 20%Oct 2026: Final finishes 20%Excavation 100%Concrete structure (RCC) 85%Final finishes 20%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%85%20%15
100%85%20%15
100%85%20%15
100%85%20%15

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

The Palladium by Fortune Reality is a 20-unit BMC-sanctioned project in Andheri East, Mumbai 400059, launched in November 2021 with possession due in April 2028. 15 units booked out of total 20 units. The concrete structure (RCC) is 85% complete.

Read full summary

The Palladium is a BMC-sanctioned project by Fortune Reality in Andheri East, Mumbai 400059, registered with MahaRERA as P51800031821. It was launched in November 2021. It has 20 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is April 2028, extended by 5 years 4 months from the original December 2022. Construction: excavation complete, structure (RCC) 85% complete, final finishes 20% complete.

15 units booked out of total 20 units (75%).