Pancham Pinnacle, Ghatkopar East

Ready to move

by Pancham Buildcon Private Limited · Ghatkopar East, Mumbai 400077 · Map

Launched
Dec 20215 yrs promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
100%Ready to move
Booked (free sale)
28 of 5848% · 22 rehab units
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale28 booked out of 58 units

Rehab22 units for existing members

Land-owner share3 units, not for sale

Total 83 units. Rehab and land-owner units are not for sale.

Project facts

Other units
83
Total units
83
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
58
Rehab units
22
Land-owner share (not for sale)
3

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services95%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 95%Jul 2026: Final finishes 95%Oct 2026: Final finishes 95%Excavation 100%Concrete structure (RCC) 100%Final finishes 95%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%28
100%100%95%28
100%100%95%28
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Pancham Pinnacle by Pancham Buildcon Private Limited is an 83-unit BMC-sanctioned project in Ghatkopar East, Mumbai 400077, launched in December 2021 with possession due in December 2026. 28 units booked out of 58 units for sale. The concrete structure (RCC) is complete.

Read full summary

Pancham Pinnacle is a BMC-sanctioned project by Pancham Buildcon Private Limited in Ghatkopar East, Mumbai 400077, registered with MahaRERA as P51800031994. It was launched in December 2021. It has 83 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Active. Of the 83 units, 58 are for sale, 22 are rehab units for existing members and 3 are the land-owner's share, not for sale.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

28 units booked out of 58 units for sale (48%).