Arunodaya Tower, Ghatkopar East
by Rajawadi Arunodaya Co-Operative Housing Society Limited · Ghatkopar East, Mumbai 400077 · Map
- Launched
- Dec 20213 yrs originally promised
- Possession (MahaRERA)
- Dec 2026Extended by 2 yrs
- Concrete structure
- 67%Mid-construction
- Booked (free sale)
- 7 of 1547% · 27 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale7 booked out of 15 units
Rehab27 units for existing members
Total 42 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 9
- 2 BHK
- 11
- 4 BHK
- 14
- Other units
- 8
- Total units
- 42
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 1
- Free-sale units
- 15
- Rehab units
- 27
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 67% | 0% | 7 | |
| 100% | 67% | 0% | 7 | |
| 100% | 47% | 0% | – | |
| 100% | 47% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Arunodaya Tower by Rajawadi Arunodaya Co-Operative Housing Society Limited is a 42-unit BMC-sanctioned project in Ghatkopar East, Mumbai 400077, launched in December 2021 with possession due in December 2026. 7 units booked out of 15 units for sale. The concrete structure (RCC) is 67% complete.
Read full summary
Arunodaya Tower is a BMC-sanctioned project by Rajawadi Arunodaya Co-Operative Housing Society Limited in Ghatkopar East, Mumbai 400077, registered with MahaRERA as P51800032224. It was launched in December 2021. It has 42 units in 1 building: 34 homes (1, 2 and 4 BHK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 42 units, 15 are for sale and 27 are rehab units for existing members.
Its registered possession date is December 2026, extended by 2 years from the original December 2024. Construction: excavation complete, structure (RCC) 67% complete, final finishes not started.
7 units booked out of 15 units for sale (47%).