Malhar Guide, Mulund West

by Atlanta Group · Mulund West, Mumbai 400080 · Map

Launched
Dec 20213 yrs originally promised
Possession (MahaRERA)
Dec 2026Extended by 2 yrs
Concrete structure
0%Early stage
Booked (free sale)
13 of 1587% · 12 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale13 booked out of 15 units

Rehab12 units for existing members

Total 27 units. Rehab units are not for sale.

Project facts

2 BHK
15
3 BHK
12
Total units
27
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
15
Rehab units
12

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Work not started as of Oct 2026

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%13
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Malhar Guide by Atlanta Group is a 27-unit BMC-sanctioned project in Mulund West, Mumbai 400080, launched in December 2021 with possession due in December 2026. 13 units booked out of 15 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Malhar Guide is a BMC-sanctioned project by Atlanta Group in Mulund West, Mumbai 400080, registered with MahaRERA as P51800032275. It was launched in December 2021. It has 27 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 27 units, 15 are for sale and 12 are rehab units for existing members.

Its registered possession date is December 2026, extended by 2 years from the original December 2024. Construction: excavation not started, structure (RCC) not started, final finishes not started.

13 units booked out of 15 units for sale (87%). Since the December 2024 update, 13 more units have been booked and the possession date has moved from December 2024 to December 2026.