Vasantoasis Blossom Bldg 20 Wing A And Wing B, Andheri East
by Neepa Real Estates Private Limited · Andheri East, Mumbai 400059 · Map
- Launched
- Dec 20215 yrs promised
- Possession (MahaRERA)
- Dec 2026Not extended
- Concrete structure
- 90%Mid-construction
- Booked
- 202 of 34958%
- Buildings
- 10.3 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 242
- 3 BHK
- 94
- Other units
- 13
- Total units
- 349
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 2
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 90% | 50% | 202 | |
| 100% | 90% | 50% | – | |
| 100% | 90% | 50% | – | |
| 100% | 90% | 50% | 202 |
"–" means MahaRERA shows no figure for that update.
About this project
Vasantoasis Blossom Bldg 20 Wing A And Wing B by Neepa Real Estates Private Limited is a 349-unit project in Andheri East, Mumbai 400059, launched in December 2021 with possession due in December 2026. 202 units booked out of total 349 units. The concrete structure (RCC) is 90% complete.
Read full summary
Vasantoasis Blossom Bldg 20 Wing A And Wing B is a project by Neepa Real Estates Private Limited in Andheri East, Mumbai 400059, registered with MahaRERA as P51800032286. It was launched in December 2021. It has 349 units in 1 building: 336 homes (2 and 3 BHK) and 13 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 90% complete, final finishes 50% complete.
202 units booked out of total 349 units (58%).
Neepa Real Estates's track record in Mumbai
MahaRERA projects registered 2017–2021 in Mumbai
| Projects registered with MahaRERA | 15 |
|---|---|
| Total units across these projects | 1,559 |
| Completed without extending the possession date | 13 |
| Completed after an extension | 0 |
| Lapsed | 1 |
| Under construction | 1 |
| Possession date extended on the builder's application | 0 |
| Typical time from launch to 100% structure | 7 years 5 months |
| MahaRERA complaints (filed by or against the builder), all Neepa Real Estates projects | 36 (11 of 15 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.