Skip to main content

Building no 3 Wing C Aquila, Kandivali East

by S D Corporation Private Limited · Kandivali East, Mumbai 400101 · Map

Launched
Jan 20224 yrs 11 mths promised
Possession (MahaRERA)
Dec 2026Not extended
Concrete structure
86%Mid-construction
Booked
118 of 14681%
Buildings
10.9 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
146
Total units
146
Buildings
1
Land
0.9 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)86%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 28%Dec 2025: Concrete structure (RCC) 28%Jul 2026: Concrete structure (RCC) 28%Oct 2026: Concrete structure (RCC) 86%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 86%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%86%0%118
100%28%0%–
100%28%0%–
100%28%0%75

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Building no 3 Wing C Aquila by S D Corporation Private Limited is a 146-unit MHADA-sanctioned project in Kandivali East, Mumbai 400101, launched in January 2022 with possession due in December 2026. 118 units booked out of total 146 units. The concrete structure (RCC) is 86% complete.

Read full summary

Building no 3 Wing C Aquila is a MHADA-sanctioned project by S D Corporation Private Limited in Kandivali East, Mumbai 400101, registered with MahaRERA as P51800032647. It was launched in January 2022. It has 146 units in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, unchanged since launch. Construction: excavation complete, structure (RCC) 86% complete, final finishes not started.

118 units booked out of total 146 units (81%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 28% to 86%.