Springwoods, Kandivali East

by Pratik Construction · Kandivali East, Mumbai 400101 · Map

Launched
Jan 20223 yrs 2 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 1 yr 9 mths
Concrete structure
92%Mid-construction
Booked
481 of 61179%
Buildings
10.8 acres
MahaRERA complaints
5Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
23
1 BHK
538
2 BHK
44
Other units
6
Total units
611
Buildings
1
Land
0.8 acres
Phases
1
MahaRERA complaints
5
Reserved units
198

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)92%
Finishes, lifts and services34%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 95%Dec 2025: Excavation 95%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 75%Dec 2025: Concrete structure (RCC) 75%Jul 2026: Concrete structure (RCC) 92%Oct 2026: Concrete structure (RCC) 92%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 34%Oct 2026: Final finishes 34%Excavation 100%Concrete structure (RCC) 92%Final finishes 34%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%92%34%481
100%92%34%481
95%75%0%–
95%75%0%185

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Springwoods by Pratik Construction is a 611-unit SRA-sanctioned project in Kandivali East, Mumbai 400101, launched in January 2022 with possession due in December 2026. 481 units booked out of total 611 units. The concrete structure (RCC) is 92% complete.

Read full summary

Springwoods is an SRA-sanctioned project by Pratik Construction in Kandivali East, Mumbai 400101, registered with MahaRERA as P51800032668. It was launched in January 2022. It has 611 units in 1 building: 605 homes (1 RK, 1 BHK and 2 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2026, extended by 1 year 9 months from the original March 2025. Construction: excavation complete, structure (RCC) 92% complete, final finishes 34% complete.

481 units booked out of total 611 units (79%).