95West, Malad West
by Stans Buildtech Realty · Malad West, Mumbai 400095 · Map
- Launched
- Feb 20225 yrs 10 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 53%Mid-construction
- Booked (free sale)
- 192 of 26473%
- Buildings
- 10.9 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale192 booked out of 264 units
Land-owner share8 units, not for sale
Total 272 units. Land-owner units are not for sale.
Project facts
- 1 BHK
- 229
- 2 BHK
- 41
- Other units
- 2
- Total units
- 272
- Buildings
- 1
- Land
- 0.9 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 264
- Land-owner share (not for sale)
- 8
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 53% | 0% | 192 | |
| 100% | 53% | 0% | 192 | |
| 100% | 16% | 0% | 188 | |
| 100% | 0% | 0% | 159 |
"–" means MahaRERA shows no figure for that update.
About this project
95West by Stans Buildtech Realty is a 272-unit project in Malad West, Mumbai 400095, launched in February 2022 with possession due in December 2027. 192 units booked out of 264 units for sale. The concrete structure (RCC) is 53% complete.
Read full summary
95West is a project by Stans Buildtech Realty in Malad West, Mumbai 400095, registered with MahaRERA as P51800032841. It was launched in February 2022. It has 272 units in 1 building: 270 homes (1 and 2 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 272 units, 264 are for sale and 8 are the land-owner's share, not for sale.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 53% complete, final finishes not started.
192 units booked out of 264 units for sale (73%).
Stans Buildtech's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 7 |
|---|---|
| Total units across these projects | 1,323 |
| Completed without extending the possession date | 1 |
| Completed after an extension | 0 |
| Lapsed | 2 |
| Under construction | 4 |
| Possession date extended on the builder's application | 2 |
| MahaRERA complaints (filed by or against the builder), all Stans Buildtech projects | 3 (2 of 7 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.